[The Badger plan was closed outside the BRAC process, so the General Services Administration has principal responsibility for its disposition. - LS]


At last, hope for reuse of Badger plant


By Scott De Laruelle
Baraboo News Republic (WI)
August 8, 2005

PRAIRIE DU SAC - Dividing 7,354 acres at the decommissioned Badger Army Ammunition Plant has not been a quick or easy process, but Saturday's gathering at the U.S. Dairy Forage Research Center farm celebrated a welcome first step. Last September, the U.S. Army turned over 1,943 acres of the plant to the federal Department of Agriculture to be used by the farm, and about 50 people turned out to officially commemorate the acquisition.

"We're celebrating the first step in the agricultural reuse of Badger," said Steve Piotrowski, assistant to U.S. Sen. Herb Kohl, D-Wis., who credited local officials and area residents for sticking with a land distribution process that likely will continue for some time. The USDA is the first entity to receive land from the plant in a land distribution process that has inched along for several years, in part due to questions about lingering contamination.

The Ho-Chunk Nation and Wisconsin Department of Natural Resources also are expected to receive land as part of the distribution process. Farm manager Rick Walgenbach said he looks forward to collaborating with both entities when their lands are transferred.

...

For the entire article, see
http://www.wiscnews.com/bnr/news/index.php?ntid=49778&ntpid=2

--
Lenny Siegel
Director, Center for Public Environmental Oversight
c/o PSC, 278-A Hope St., Mountain View, CA 94041
Voice: 650/961-8918 or 650/969-1545
Fax: 650/961-8918
http://www.cpeo.org

_______________________________________________
Installation_Reuse_Forum mailing list
Installation_Reuse_Forum@list.cpeo.org
http://www.cpeo.org/mailman/listinfo/installation_reuse_forum

  Prev by Date: [CPEO-IRF] Skyline Complex, Falls Church (VA)
Next by Date: [CPEO-IRF] Heritage Foundation on BRAC recovery
  Prev by Thread: [CPEO-IRF] Skyline Complex, Falls Church (VA)
Next by Thread: [CPEO-IRF] Heritage Foundation on BRAC recovery

CPEO Home
CPEO Lists
Author Index
Date Index
Thread Index