Navy Begins Demolition of Six Buildings at former Hunters Point Naval Shipyard in San Francisco
by Christopher Dunne 
Naval Facilities Engineering Systems Command HQ
March 5, 2026
SAN FRANCISCO – Work has begun on the abatement and removal of hazardous materials for six buildings scheduled to be demolished at the former Hunters Point Naval Shipyard under a contract awarded to Burlingame, California-based ECC.
Demolition of buildings 351, 351A, 366, 401, 411 and 439 is slated to begin in late March, with planned completion within 15 months.
“This contract begins the congressionally authorized building removal work at the former Shipyard, said Michael Pound, the Navy’s Base Realignment and Closure (BRAC) environmental coordinator for the property. “We will work closely with the contractor to remove these structures with minimal impact to surrounding communities and businesses.”
…
For the entire release, see
https://www.dvidshub.net/news/559417/navy-begins-demolition-six-buildings-former-hunters-point-naval-shipyard-san-francisco
—
Lenny Siegel
Executive Director
Center for Public Environmental Oversight
A project of the Pacific Studies Center
LSiegel@cpeo.org
P.O. Box 998, Mountain View, CA 94042
Voice/Fax: 650-961-8918
http://www.cpeo.org
Author: DISTURBING THE WAR: The Inside Story of the Movement to Get Stanford University out of Southeast Asia - 1965–1975 (See http://a3mreunion.org)
_______________________________________________
Military mailing list
Military@lists.cpeo.org
http://lists.cpeo.org/listinfo.cgi/military-cpeo.org
|