From: | Lenny Siegel <lsiegel@cpeo.org> |
Date: | 2 Feb 2007 22:06:14 -0000 |
Reply: | cpeo-irf |
Subject: | Re: [CPEO-IRF] New GAO report on closure environmental issues |
The new GAO report on base closures is a cursory review of the
environmental cleanup challenges at base realignment and closure sites.
It says, once again, that costs will go up and that there are many ways
to convey property. Unfortunately, its bean-counting approach does not
does not provide the in-depth analysis necessary to understand the
implications of the 2005 round of Base Realignment and Closure (BRAC).
For example, it states that the 102,000 acreage for BRAC 05 "includes acreage at three chemical demilitarization bases slated for closure - Deseret Chemical Depot, Utah; Newport Chemical Depot, Indiana; and Umatilla Chemical Depot, Oregon." But it never explains that those properties won't be transferred until they complete their chemical weapons disposal missions. Understanding partial or full transfers at those three facilities is significant, since those three facilities total 46,000 acres, nearly half the total. GAO also provides data, compiled from the Defense Environmental Program Annual Report for 2005, showing that BRAC 05's environmental problems are much smaller than those of previous rounds, but I didn't notice any emphasis on that point. There are only three major cleanups (over $25 million cost to complete) on the 05 list, but the top ten from previous rounds are all above $75 million. BRAC 05 TOP THREE Fort Monroe (VA) $201 million Deseret Chemical Depot (UT) $178 million Concord Naval Weapons Station $85 millionIt would have been helpful to see a discussion of undetermined munitions response requirements at Fort Monroe and a discussion of potential chemical warfare recovery and disposal at Deseret. The discussion of different conveyance methods doesn't address the pros and cons of each, but Table 6 is the best compilation of Early Transfers that I've seen: Table 6: Use of Early Transfer Authority at Prior BRAC Round Bases, as of July 2006 Installation Acres Fort McClellan, Alabama 4,692 Naval Shipyard, Mare Island, California 3,486 Fort Devens, Massachusetts 2,358 Alabama Ammunition Plant, Alabama 2,235 Naval Air Station Memphis, Tennessee 1,863 Naval Air Station Agana, Guam 1,798 Tooele Army Depot, Utah 1,621 Naval Activities, Guam 1,482 Fort Ord, California 1,401 Fleet Industrial Supply Center, Oakland, California 676 Naval Shipyard, Charleston, South Carolina 436 Oakland Army Base, California 364 Grissom Air Force Base, Indiana 201 Bayonne Military Ocean Terminal, New Jersey 192 Griffiss Air Force Base, New York 179 Mather Air Force Base, California 165 Wurtsmith Air Force Base, Michigan 149 Naval Ordnance Station, Louisville, Kentucky 142 Fitzsimons Army Medical Center, Colorado 133 Naval Training Center, San Diego, California 51 Public Works Center, Guam 25 Lowry Air Force Base, Colorado 12 Naval Training Center, Orlando, Florida 9 Total acres 23,670 Lenny Lenny Siegel wrote: MILITARY BASE CLOSURESOpportunities Exist to Improve Environmental Cleanup Cost Reporting and to Expedite Transfer of Unneeded PropertyU.S. Government Accountability Office January 30, 2006 GAO-07-166 To download the entire report, go to http://www.gao.gov/cgi-bin/getrpt?GAO-07-166 HighlightsWhile expected environmental cleanup costs for unneeded property arising from the 2005 BRAC round are not yet fully known, Department of Defense (DOD) data indicate that about $950 million will be needed to clean up these bases, adding to the estimated $13.2 billion total cleanup cost for the prior rounds. Although DOD's cleanup program has matured compared to prior BRAC rounds, there are still many unknowns and the cleanup estimate for the 2005 round should be considered preliminary. In fact, environmental cleanup costs are likely to increase as more intensive environmental investigations are undertaken, additional hazardous conditions are discovered, and future reuse plans are finalized. Furthermore, Congress does not have full visibility over the total cost of DOD's BRAC cleanup efforts because none of the four reports DOD prepares on various aspects of environmental cleanup present all types of costs-past and future-to complete cleanup at each base. Compiling a complete picture of all costs requires extracting information from multiple reports, as GAO has done to estimate the total cleanup cost for the four prior BRAC rounds. More complete and transparent cost information would assist Congress in conducting its oversight responsibilities for this multibillion dollar effort.While GAO's analysis shows that DOD continues to make progress in transferring over 502,500 acres of unneeded property from the four prior BRAC rounds-78 percent of the acres have now been transferred compared to 72 percent 2 years ago-over 112,300 acres remain untransferred. Comparatively, a total of about 102,000 acres are potentially transferable as a result of the 2005 BRAC round. Impediments to transfer continue to be related primarily to a variety of interrelated environmental cleanup issues, including limited technology to address unexploded ordnance and prolonged negotiations on compliance with environmental regulations.Opportunities exist to expedite the cleanup and transfer of unneeded 2005 BRAC properties compared with other BRAC rounds. Congress provided DOD with a wide range of property transfer authorities for prior BRAC rounds. In the past DOD did not use some tools as much as others out of deference to community land reuse plans. For example, low- and no-cost transfer tools accounted for 65 percent of all acres transferred, whereas public and negotiated sales accounted for 5 percent. DOD's March 2006 guidance now encourages the services to make full use of all tools for transferring properties resulting from both the 2005 and prior-year BRAC rounds. The services have processes in place to monitor their progress to clean up and transfer BRAC properties, but they are not required to report periodically to the Office of the Secretary of Defense on their successes and challenges in using various transfer authorities. Collectively, such lessons learned could help others expedite the cleanup and transfer of unneeded properties by maximizing the use of all available tools, thereby accelerating the economic benefits of property reuse to communities while also saving the ongoing caretaker costs being incurred by DOD for unneeded propertie -- Lenny Siegel Director, Center for Public Environmental Oversight c/o PSC, 278-A Hope St., Mountain View, CA 94041 Voice: 650/961-8918 or 650/969-1545 Fax: 650/961-8918 <lsiegel@cpeo.org> http://www.cpeo.org _______________________________________________ Installation_Reuse_Forum mailing list Installation_Reuse_Forum@list.cpeo.org http://www.cpeo.org/mailman/listinfo/installation_reuse_forum | |
References
| |
Prev by Date: [CPEO-IRF] New GAO report on closure environmental issues Next by Date: [CPEO-IRF] Ft. Monroe (VA) proposal | |
Prev by Thread: [CPEO-IRF] New GAO report on closure environmental issues Next by Thread: [CPEO-IRF] Ft. Monroe (VA) proposal |