Subject: [CPEO-MEF] REUSE, ENERGY: "Dominion: Federal government should pay $13 million cost of upgrading Fort Monroe's [VA] electrical system"
 
Dominion: Federal government should pay $13 million cost of upgrading Fort Monroe's electrical system


by Peter Dujardin 
Hampton Roads Daily Press (VA)
October 2, 2018

Dominion Energy is suing the federal government over needed electrical upgrades at Fort Monroe — saying the government should bear the $13 million cost of bringing the old U.S. Army base up to current standards.

When it was an active Army post, Fort Monroe was exempt from lots of existing state regulations on electricity.

But the base was closed in 2011.

Among the necessary improvements, Dominion says it now must add separate meters at Fort Monroe’s 224 buildings — including residential homes — rather than the single “master meter” that serves the base now.

…

For the entire article, see
http://www.dailypress.com/news/hampton/dp-nws-fort-monroe-electricity-lawsuit-20181002-story.html

--

Lenny Siegel
Executive Director
Center for Public Environmental Oversight
a project of the Pacific Studies Center
P.O. Box 998, Mountain View, CA 94042
Voice/Fax: 650/961-8918 
<lsiegel@cpeo.org>
http://www.cpeo.org

_______________________________________________
Military mailing list
Military@lists.cpeo.org
http://lists.cpeo.org/listinfo.cgi/military-cpeo.org
  Prev by Date: [CPEO-MEF] PFAS: "[Federal] Court sets precedent, rules Navy can be sued for PFAS claims"
Next by Date: [CPEO-MEF] GLOBAL, REALIGNMENT: "New governor vows all-out efforts to block base move within Okinawa, " Japan
  Prev by Thread: [CPEO-MEF] PFAS: "[Federal] Court sets precedent, rules Navy can be sued for PFAS claims"
Next by Thread: [CPEO-MEF] GLOBAL, REALIGNMENT: "New governor vows all-out efforts to block base move within Okinawa, " Japan

CPEO Home
CPEO Lists
Author Index
Date Index
Thread Index